April 1996 | Preliminary Engineering Report (PD&E) |
August 1996 | Location and Conceptual Design Acceptance |
April 2000 | Segment 1 Value Engineering Study |
May 2000 | Key Stakeholder's Workshop |
October 2000 | Segment 2 Value Engineering Study |
April 2001 | Strategic Corridor Planning Study Ends |
September 2001 | Segment 3 and 4 Value Engineering Study Begins |
November 2002 |
Right-of-way Acquisition Begins (Project #22773-1: 1200' south of County Line Road to SW 25th Street) |
December 2004 |
Right-of-way Acquisition Begins (Project #227774-1: SW 25th Street to Fillmore Street) (Project #227776-1: North of Seminole Way) |
December 2006 | Construction Begins (Project #22773-1) |
December 2008 | Construction Begins (Project #227774-1 & 227776-1) |
|